The Berlin event
Dardania AI’s GTC Berlin announcement invited prospective customers and partners to discuss infrastructure requirements for 2027 and beyond. The event was scheduled for October 20–22, 2026 at STATION-Berlin.
Capacity and architecture
The proposed first phase provides 300 MW through 50 MW deployment blocks, with initial energization targeted for 2027. The technical approach combines NVIDIA’s Vera Rubin DSX reference architecture with Vertiv power and liquid-cooling systems.
Power and data sovereignty
Other discussion topics included generation-backed electricity supply and infrastructure intended to support GDPR and EU data-residency requirements. The energy strategy aims to serve the campus without competing with local consumers.
Continue the conversation
For current capacity discussions or a meeting with the team, contact Jon Kondo at jon@dardania.ai.
Explore the next phase.
Talk about capacity